It takes 5 men 12 days ro complete a job how many days does it take 3 men to complete the job

Respuesta :

eloo59980
eloo59980 eloo59980
  • 04-01-2021

Answer:

5=12

3=? then Criss cross it and you will get 12*3 divided by 5 then you get 7.2

so the answer will be 7 days