It takes 2 workers 6 days to paint a mansion. How many days would it take 4
workers to do the same job?

Respuesta :

dontmindme3
dontmindme3 dontmindme3
  • 01-03-2021

Answer:

2 workers = 6 days

4 workers = 3 days

Step-by-step explanation:

If it takes 2 workers 6 days, if you seep up the process with 4 workers, you would divide the days by 2 because you multilpied the workers by 2. So, it would take 3 days with 4 workers. I hope that makes sence.

Answer Link

Otras preguntas

The following are four largest country's in the world Russia Canada China united states what country located in south america also ranks as one of the ten large
the blueprint for landscaping a yard has a scale of 1/2" to1 foot. if the blueprint is a rectangle 18 inches by 22 inches,what are the dimensions of the yard?
Write the name of a shape that has no sides and no vertices
How are continental volcanoes formed?
WRITE EACH RATE AS UNIT RATE. 162 WATER BOTTLE IN 9 CASES=
2x-y=-63x-4y=-4Solve using elimination and then substitution
Which three countries have the least access to technology?
what is £42 increased by 10%
What two numbers has a lcm of 50
The cost for n students to attend a workshop is 7n+12 dollars. What is the cost,in dollars for  students to attend?