Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Prove <5 is supplementary to <6 using theorems.
Psychology Short Essay 100 points and Brainliest quick!!!!!!! 40. Discuss some of the reasons suggested that we need sleep, and then explain what happens during
In each figure, solve for X
NEED HELP ASAP! TYSM IF YOU DO Which of the following equations represents the greatest value of x? Equation 1 x^2 = 17 Equation 2 x^2 = 26 Equation 3 x^3 = 64
HEELP PLEASE! What is a cardiac style???
AHHHHHHHHHHHH please help me!!)) This comparison using like is an example of _______.The train shot through the night like a bullet.personification a rhymea sim
slope=1/3 y intercept=-1
Expand and simplify the following √3 (√3 - 1)√5 (√10 + √2)​
I rlly need help it’s due tmrw
[tex]2 {}^{3} \times 2 - {}^{3} [/tex]I need answers ​