Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

past perfect tense: the storm STOP by early afternoon.
For f(x)=3x+4, find f(2) and find x such that f(x)=17
The Earth has a radius of 6,400 kilometers. A satellite orbits the Earth at a distance of 12,800 kilometers from the center of the Earth. If the weight of the s
Which sign is the less sign and which one is the greater sign (can someone please tell me I really need help! and I never understand the signs!) is this greater
Who benefitted from the corrupt bargain?
what is the term for the condition where red blood shrivels?
Hitler intended to defeat great Britain by
How long does water evaporation take? What factors influence it?
solve the proportion2x + 1/x + 1 = 14/3x-1
Which of the following nutrient cycles has its largest reservoir in the atmosphere? A) Carbon cycle B) Nitrogen cycle C) Potassium cycle D) Phosphorus cycle E)